16 May Case Study – Overlay to Raised Access Floor – Knauf GifaFloor FHB18
Overlay to Raised Access Floor – Knauf GifaFloor FHB18
Timescales: July – November 2022
Project Size: 925 m2
Products: Knauf GifaFloor FHB18 – Load Bearing Dry Screed Panel
Client: Arena Stone & Ceramics
Location: 60 London Wall, London, EC2M
60 London Wall is an icon office building in the dynamic heart of London’s City, with 328,500 sq ft of grade A office accommodation situated over ten stunning floors.
Alliance Bernstein now occupies office space within the building. The CAT A fit out originally meant that bare steel raised floor panels had been installed within the area. A ceramic finish was included within the new fit-out design, to be installed at various locations with the space.
Knauf GifaFloor FHB18 structural panel was specified to overlay to the existing raised floor to create an ideal substrate for the hard finishes to be applied.
From start to finish AFD and the team could not be more helpful. Information on the products was always to hand at a moments notice. Deliveries were within a day or two as required then transported into the building to a professional level. Across the 925m2 gifa floor we have not had any quality issues with the boards / glue or tape.
AFD delivered GifaFloor FHB18 over 3 call offs using FORS Silver transport vehicles, and a fourth delivery at short notice for additional accessories required
Congrats to Arena Stone & Ceramics for such a fantastic finished product
For more information regarding the Overlay to RAF Systems available – Click here